Monday, April 29, 2013

GIS II Project ~ Phase 4


Introduction:


Lab 5’s goal is to familiarize myself with raster analysis while developing a faux model for terrain suitability and environmental risk of sand mining in Trempealeau County, WI. I will use Elevation, Land Use-Land Cover, Slope, Water Table, and Railroad rasters to determine optimal locations for a sand mine in the county; then DNR hydro, prime farmland, county schools, recreational, and existing mine data will be used to determine locations within the county where a silica sand mine is not desirable. These two indices will then be compared to find the optimal locations for construction of a new mine.



Methods:

   Part I

Fig 1: Suitability Index

The first section, the suitability index (fig 1), begins with the consideration of geologic bedrock data gathered from the MRLC. The Wowenoc and Jordan formations are given as significant locations of silica sands, however the data provided is only a raster base map. There are two options for how to proceed to get this information into a format that can be analyzed: digitization (with which we are familiar) or elevation can be, in this case, used to interpolate the location of these formations because of a relationship between surface elevation and the formation of these bedrock layers. This process consisted of developing contours from the Digital Elevation Model retrieved from the Trempealeau county geodatabase, then comparing them against the geologic formations given in the base map.

Once the elevation range for these layers was determined, a ranking of the county’s territory was developed by reclassifying the original DEM into three regions delineated by elevational proximity to the aforementioned elevation ranges correlating with the Jordan and Wowenoc formations.  The regions that best fit the geologic layers were given “high” ranks of three, and the most distant received ranks of one.

With the DEM, the slope tool was also used to find %rise/%run in the county. From this data, Trempealeau was also divided into three regions based on the suitability of an area’s slope for construction (smaller slope=better).  Again, this coefficient was ranked one to three, as are the rest of the interpolated values.

The land use raster that was downloaded for Lab 3 was also used in the terrain analysis for this Lab: the county was reclassified based on the suitability of each area for constructing a mine. For example, an open field or barren land would be ranked highly whereas a forest would rank low because of the differential in ease of construction between the two parcels.  

The last factor considered in land suitability for the sand mines was the water table level. Silica sand mines use water in the process of extracting sand, therefore a higher water table (closer to the ground surface) merited a higher suitability coefficient.  The exact cutoffs for these factors were determined by examining the histograms of the final rasters produced, that values can be found in the table appended to the end of the methods section.

Finally, Raster Calculator was run to add the three coefficients together, piecing together the final Trempealeau Silica Sand Mining Suitability Index. Five coefficients ranked 1 to 3 means a range of 5 to 15.  Areas of urbanization and open water were also removed from the index, because it would be entirely impractical to construct a mine in those locations if not impossible.  The final mapped index can be found in the results section below.


   Part II

Fig 2: Unsuitability Index


The second portion of this exercise is to find areas in which a silica mine would be unsuitable for its surroundings, in particular the environment and local residents (Data Flow model in fig 2). This begins with an examination of potential impact of a silica sand mine on Trempealeau streams. To determine the risk of impact, a Euclidean Distance tool was used to find the distance of each cell within Trempealeau County from the nearest stream. From this distance, the county was divided into three regions of contamination risk determined by that distance. After viewing the stream-distance data that was generated, the region was ranked into three areas representing proximity to major streams.  This method is similar to the method for part I, however where in part I areas of high desirability were ranked highly, the opposite is true here and areas most suitable are ranked at a lowly one.

Schools, residential zones, and existing mines are similar to streams in that proximity to them is undesirable, and as such they both used a similar method to divide the county into zones of proximity. The difference with these two features was that they weren’t discrete features in the data provided by Trempealeau County; however they could be derived from the parcel and zoning data that was provided. The features were first selected out, then had the Euclidean Distance tool applied to them before finally being reclassified. Also, because of the intense noise produced by mining operations, it has been determined that 640 meters is the minimum distance that they should be located from hoses or schools, therefore those regions were excluded from the final analysis by using the Boolean “And” in raster calculator.  As for the distance from preexisting mines, obviously it is detrimental to compete for sparse local resources in addition to extra taxing on the local atmosphere to place mines too nearby.  Therefore a distance tool was run similar to above.

Agriculture is integral to the economy of Wisconsin, and Trempealeau County is absolutely an example of this. As such, in the Trempealeau County geodatabase that had been downloaded is data for “prime farmland,” agricultural land which is important not just to the local farmers but to the state as a whole.  This prime agro land is what received the highest value in this section of the exercise, and lands that were designated as never good for farmland received the highest.

The last coefficient to be determined was the effect of potential mines on recreational tourism in the area, in particular on the hiking trails.  The factors for both models are given in Fig 3 below.

The Suitability Factors used for Trempealeau County

Fig 3: Suitability Indices



Sources:


Trempealeau County Geodatabase, downloaded from the official Trempealeau County Land Records Division http://www.tremplocounty.com/landrecords/.

National Land Cover Database from the Multi-Resolution Land Characteristics Consortium. http://www.mrlc.gov/nlcd01_leg.php

Wisconsin Geological and Natural History Survey’s digital dataset of Trempealeau County: http://wisconsingeologicalsurvey.org/gis.htm



Results:

Fig 4: Suitability Index

Fig 5: Unsuitailibty Index


The results of the analysis (indices 4 and 5) speak for themselves.  Urban areas are clearly to be avoided in developing a new sand mine, especially particular to this was the exclusion of 640 meters around residential and developed land in the Unsuitability Index, with large swathes cut out around the relatively quite small urban areas in the county.  For comparison, I have included a model without the exclusion of these areas as to view the (un)suitability of the area excluded by this single factor (fig 6).  These indices could be subtracted from one another in order to derive a general suitability model for Sand Mining in the county.
Fig 6: Unsuitailibty Index, with urban areas included.

Saturday, April 27, 2013

Lab 4 ~ Habitat Suitability


Introduction:

            The goal of this Lab was to familiarize myself with some overlay, generalization, and extraction tools integral to GIS while building a habitat model for black bears in an area of interest which focused in Marquette County, MI.  Ultimately, I intend on importing x,y data to the GIS, determine if bears can be found near streams, figure a suitable habitat for bear management and provide a cartographically pleasing map to showcase my effort.  I will also develop a data flow model to document my methodology.



Methods:






Results:






Sources: Source Data was obtained from the Michigan Geographic Data Library thru Professor C. Hupy.

Sunday, April 14, 2013

Lab 3 ~ The Handheld GPS


Introduction and Background:

                For this lab, the objective is to simply digitize a handful of real-world features into a GIS by using a Global Positioning System (GPS).  Martin Goettl and the UWEC Geography Department provided the students with Trimble Juno handheld GPS units with which we would collect point, polyline, and polygon features nearby on campus.  Before collecting the data, we will need to familiarize ourselves with geodatabase construction and deployment of a geodatabase to a mobile device using ESRI ArcMap and ArcPad.  Finally, we are going to import the data back onto the computer and develop a cartographically pleasing product which shows three trees and lightposts, three triangular plots (which will turn to lawn in the spring), a nearby circular sidewalk feature and the nearby bridge.

 

fig 1 The Juno. Pulled from the interweb, this was not my exact Juno. It is the right model though. Virtually identical.


Methods:

                Step one is to develop a geodatabase using the Arc platform.  In our case, using ArcCat 10.1, this is accomplished by right clicking on the folder where the database will be stored, then under ‘new’ either “File-” or “Personal Geodatabase” is selected (fig 1).  Using a similar method, but clicking this time on the database, three new feature classes were developed: one point, one line and one polygon.  The feature classes were created using the NAD83 Wisconsin HARN in meters because it is a fairly accurate projection which is common throughout the state.  Also created was a field for each labeled “type.”    The ArcPad Data Manager extension in ArcMap was then used to export the data to the Juno device.

fig 2 adding a geodatabase
                With the important information loaded onto the handheld GPS, it was taken outside to collect the required feature data.  Before doing so, it needs to be ensured that the GPS unit’s almanac is up to date and if it needs updating the user should be sure to do so (fortunately, mine was fully updated).  To digitize the data, I used point averaging to collect the lights and trees (points) as well as the vertices of the triangles and circle.  Instead of using point averaging, I tried a tracklog for the bridge over the creek (which collected my position at points over a time interval).

                Finally, the data was uploaded to the computer using the Data Manager described earlier.  As a couple of triangles had extraneous vertices, possibly from user error, I edited these points out of the data.  It was then symbolized and made into a map.

fig 3 My raw data was contaminated by extra vertices. They could either be GPS burps, or user error. It is impossible to say for certain.
 
Results and Discussion:

                Completion of the project itself required relatively few steps), though learning to successfully navigate the foreign ArcPad controls was something of a headache for myself, which perhaps led to my interesting polygon features (fig 3).  This can be easily fixed in the Juno unit or in ArcMap though.  If I were to redo the project, I would definitely rely on point averaging for the path across the bridge, because -not surprisingly- the tracklog does not provide as accurate data as the point averaging.  This is not to imply that the average of ten points with the small Juno unit is necessarily accurate, because as can be seen in the final result it is not.  Well, it is to a point.  That point just happens to be small features such as the smaller triangles and circle.  In fact, I am a little surprised that my circle is as circular as it is.

fig 4 My final Presentation
The background aerial imagery given for the project was a year or so old, and had not been updated to reflect the fact that a fairly large neighboring building had been demolished, and a replacement built to its south.  The sidewalks over the area have been completely altered, and another completely new building in the north is in the process of going up, so the features I processed seem fairly out of place on the given image.  I pulled a more recent image from another class which was aerially mapping campus and had taken an image less than a week before I digitized the features.  The difference in the presentation of the final project is staggering.

Monday, April 1, 2013

GIS II Project ~ Phase 3 Network Analysis

Introduction:

     The function of this exercise is to develop some basic network analysis skills by working with the mine data developed in Phase 2.  During this project, I will load the geocoded locations of the silica mines in Wisconsin along with given state road data and locations of state railroad terminals.  I will run an analysis along the road network to find the most efficient route from the sand mines to rail terminals: shorter routes are desirable because a shorter route means lower time and gas requirements of getting the sand to market which adds up very quickly over the life of a silica mine.  After completion of this task, I will parse out these optimal routes by county and estimate the cost to each county for infrastructure maintenance related to the transportation of these operations.


Methods:

     As described in the intro, the first step in this process will be to import the mines, roads, railroad terminals, and counties into a GIS.  Fortunately, all of the data has been compiled (in the previous exercise) and is projected appropriately, so it  will merely be relocated to a central geodatabase for use in this project.  Once all of the base data is in the desired place, the network analysis can begin.

fig 1: the results of the route tool, interesting but not helpful to us today.
     Using Arc, the network analyst toolbar first needs to be initiated before beginning, and I recommend the toolbar be used to easily navigate the tools as opposed to scouring the toolbox for each step of processing.  The first tool that will be run is "new route" analysis to find one potential path that would include all of the mine locations as "stops."  This was mostly done to explore what the tool was useful for, but the result will not be of any use to us as our goal is to find paths from each mine to the nearest rail terminal, not a single route which connects each mine. That route would not be useful for very much.



     In order to determine the optimal routes from mines to rail terminals, the Closest Facility tool will need to be used, this process is described in the data flow model below (fig 1).  This tool uses the location of a set of "facilities" and "incidents" within a network such as a roads feature class.  Once it has determined those locations, the tool can consider additional parameters to the analysis such as whether or not the roads being used have a hierarchy , for example if one would rather drive on a highway than backwater streets.  Once the facilities (terminals), incidents (mines), network (roads) and optionally barriers have been set, the tool can be run.  Upon completion, the tool will provide a "Routes" dataset which is a collection of the fastest paths from each mine to each terminal.



fig 2: the final data flow model for this project.


     Once the routes have been found, the next task of the project is to determine the cost of each mine to the county for road maintenance.  The first step here is to parse out the route data by county, which can be accomplished easily enough by intersecting the routes feature class to a county feature class and then running the statistical summarize tool.  This gives a feature class of each county's routes used by the network analysis.  Then, in the attribute table which contains the data for each county's routes, a new (float) field was created which ran each route summary through an equation that was determined to roughly estimate the cost to each county of each mile of road.   This entire process was completed with the Model Builder tool, and this was the first project on which I worked with the Model builder.  The final model is given as figure 2.

fig 3: the calculation of cost per county



     The equation given was 100*[Miles]*0.022. The coefficients were determined as follows: each mine can expect to make 50 trips in a truck to each terminal (and 50 trips back), and the cost to the county is 2.2 cents per mile.  Therefore, the annual cost to each county in Wisconsin for road maintenance because of these silica mines is described as 2.2(miles), or as expressed in the Arc as described above (fig 3).  With the cost to each county estimated, the final maps for this project could be developed and are provided in the results section below.

Results:

fig 4: the results of the closest facility tool

fig 5: the results of the final analysis with cost per county symbolized.
 


Discussion:

     The results of this analysis may have been skewed by a couple of factors.  First and foremost, because of the scope and goals (educational) for this project a number of assumptions were made.  The number of trips that each truck was sent on to the nearest terminal was 50 per year, which seems extremely low.  Also, many mines have rail lines that pass through them in to which they are connected and therefore they do not need to drive to a terminal, costing the county in some cases millions of dollars.  Finally, it may have been unfair to use a different source and set of methods for Trempealeau County's mines than for other counties', as the TC mines were pulled from a geodatabse where every single mine was listed and addressed in the county which probably artificially raised the costs of this county in the analysis significantly.

     I learned to highly value the model builder in this project.  It helps to keep track of what I'm doing and organize my project to help give a clearer vision of what needs to be accomplished as the analysis continues. I also gained an appreciation for county webservers which provide accurate, high-quality information freely to the public.